Power Infrastructure and Redundancy
Our power architecture is engineered to support mission-critical AI hardware, including NVIDIA Hopper and Blackwell architectures.
Substation and Distribution
- Transformer Capacity: The facility features four main substations and three auxiliary substations, each providing 1.25 MVA.
- Bus Bar Configuration:
- Data Hall 1: 4 x 3-phase bus bars (250 kW each)
- Data Hall 2: 2 x 3-phase bus bars (500 kW each).
- Distribution Infrastructure: Power is delivered via APC Schneider Electric bus bars and Vertiv Geist intelligent PDUs.
- Output Options: Supports 3-phase (3 x 32A or 2 x 32A) and 1-phase 16A outputs through single breaker outlets.
Backup and Protection
- UPS Configuration: Isolated redundant systems provide $N+1$ protection for all critical loads.
- Standby Generation: Dual 250 kW generators provide standby power redundancy ($N+1$).
- Overvoltage Protection: Coarse protection is applied at the transformers, with medium protection maintained on all bus bars.